Siting Hokkaido’s first nuclear plant — moving it from inland to coastal Tomari (1978)
What could be conceded, and what could not
Read the Tomari siting as the fruit of patiently persuading the locals and you lose sight of the move that actually worked. Nine years passed from the choice of a site, and what had stalled the negotiation was not a shortage of persuasion but the plan itself — a scheme to carry nuclear fuel and waste by dedicated road from Iwanai port. By moving the site to coastal Tomari village in 1978 and erasing that transport route, the fishery cooperatives that had kept opposing shifted to conditional approval. Placing the object of concession in the content of the plan rather than in the technique of negotiation can be seen as the core of this judgement.
Yet meeting the requirements and winning understanding were two different things. Even after the fishery compensation agreement of September 1981 satisfied the three conditions the state required, Hokkaido after Chernobyl saw a petition of 800,000 signatures submitted to the governor, and unit No. 1 began operating in June 1989 with that opposition still in place. Local agreement could be obtained by moving the site; prefecture-wide opinion would not move by the same means. These fifteen years show that siting a nuclear plant required two separate consents.
Revenue and net margin, FY1973–FY1983
Revenue in ¥ bn (bars) and net margin in % (line), for the years around the decision. Shaded columns are FY1978 onwards — after it was taken.
Source: securities reports
Read the full dossier in Japanese →
The Japanese edition carries the complete record of this decision — the situation that forced it, the options weighed, what actually followed, and the sources behind every claim.
Other key decisions at Hokkaido Electric Power
Yen amounts are converted at the average rate of each figure’s own year — not today’s rate; the revenue chart is shown in yen. Exchange rates & sources — the full ¥/US$ table →
Disclaimer
- This page is provided for general information only and is not investment advice, nor a recommendation to buy or sell any security.
- Figures are compiled independently and include our own estimates, approximations and machine-processed data; we make no warranty as to their accuracy or completeness.
- Sources are primarily each company’s securities reports and other public filings, but errors and omissions may remain.
- Any use of this information is at the reader’s own risk. Past performance does not indicate future results.
- Company names, logos and other marks belong to their respective owners.
Data API
Hokkaido Electric Power’s history, financials, executives and
shareholders are published as static JSON — no key, plain GET.
Full specification →
| Method | Endpoint | Returns |
|---|---|---|
| GET | /api/companies.json | All companies |
| GET | /api/9509/manifest.json | Resource index |
| GET | /api/9509/history.json | History overview |
| GET | /api/9509/timeline.json | Chronology |
| GET | /api/decisions.json | All management decisions (index) |
| GET | /api/9509/decisions.json | Management decisions (index) |
| GET | /api/9509/decisions/{slug}.json | One decision (full dossier) |
| GET | /api/9509/executives.json | Executives |
| GET | /api/9509/shareholders.json | Major shareholders |
| GET | /api/9509/financials.json | Financial statements |
| GET | /api/9509/financials-longterm.json | Long-term results |
| GET | /api/9509/segments.json | Business segments |
| GET | /api/9509/regions.json | Sales by region |
| GET | /api/9509/workforce.json | Workforce |